We met with the full SoleCrypt team at T60 in Tozeur, our flagship 60 MW solar and digital-infrastructure site, for an on-site working session. The visit came at a key moment: fencing and base-camp installation are now complete, securing the land and enabling the next phase of field operations.
This offsite was not symbolic; it was operational. Walking the full perimeter, reviewing the site layout, and aligning on sequencing allowed the team to consolidate technical context and confirm the immediate milestones required to keep development on schedule.
Later in the day, we welcomed HMA Roddy Drummond and representatives from the British Embassy in Tunisia for a brief on-site walkthrough. Their engagement supports the BritishโTunisian Strategic Collaboration Framework (2022), which prioritises renewable-energy investment, resilient digital infrastructure, and skills-transfer across both regions.


Highlights from the Visit
โข Major site milestone: Perimeter fencing and base-camp setup completed at T60
โข Team alignment: Operational offsite focused on sequencing, risk checks, and short-term execution
โข Diplomatic engagement: On-site acknowledgment and thanks to UK Embassy representatives
โ

Whatโs Next
With the site fully secured and the base camp operational, we now move into the next stage of on-site activities:
โข ground-profiling and layout validation
โข preparation for technical contractors
โข continued coordination with local authorities and national stakeholders
Regular field updates will follow as we advance development of one of Tunisiaโs most strategically located solar-powered compute hubs.
Acknowledgements
To the team on the ground in Tozeur: your consistent execution is driving this project forward.
To our partners at the British Embassy: thank you for your continued engagement and alignment.